The gasskid of unit EC 4 in a different angle.
In this skid the gas is heated up from appr. 15°C to max. 95°C (203F) in order to keep combustion stable.
Gasconsumption of this unit is appr 55000 m³ per hour.
We're about to start up unit EC 4 by request of TenneT, the system operator.
We have to consume reactive power (MVar) to maintain the conditions of the high tension grid in limits. So we deliver our minimum load in MegaWatts and consume reactive power.