Load bearing

I had an earlier than usual start today to make sure I was on site for the guys to fix the steel supports to resuspend the 4 big air-con units in the lab. The issue is that it needs the analysers shut down and covered so that no dust can get sucked into them. It's a hassle but means we can finally get rid of the temporary support struts. The original plan I signed off was to get the first unit done, then make a plan for the others based on how long it took. As it panned out the plan changed to get the first 3 done so that the analysers only had to be shut down once on one day. The last unit will be done tomorrow, as it will need the other analyser shut down.

I didn't even get to leave early in the end... 